About Imatech
|
Supplier Links
|
Cart
|
Contact Us
Home
Products
Case Histories
Order Online
Case Study
Industrial Corrosion & Abrasion
Mine Backfill Solutions
Water Treatment and Filtration
Ultra-Resistant Wear Liners
Weigh Hopper, Steel Works
Transfer Chute, Steel Works
Head Chute Dead Bed, Nickel Processing
Tertiary Crusher Feed Bins, Iron Ore
SAG Mill Discharge Chute, Nickel
Port Loading Facility, Iron Ore
Apron Feeder Chute
Transfer Chute, Iron Ore
Iron Ore & Coal Transfer Chute
Reclaimer, Centre Chute
Non-Slip Safety Surfaces
Pump Refurbishment & Improvement
Transfer Chute, Steel Works
Industry
Steel Works
Site
NSW, Australia
Application
Conveyor Transfer Chute
Problem Description
Original liner material wore out before 18-weekly scheduled maintenance shutdown, causing unscheduled shuts, disruptions and high costs
Imatech Solution
A 5 year comparative test was carried out to determine the best liner solution:
The Results
Based on the apparent wear patterns after change-out at 62 weeks, Imatech has reviewed the design to further extend the total wear-life. The current target is to achieve a 72-week wear life, coinciding with every 4th shut.
Search
Website Development by The Pagesmith
COPYRIGHT © 2010 IMATECH ABN 49 063 145 960
TOLLFREE (+61) 1800 352 228 PHONE (+61) 02 8853 3000
CONTACT IMATECH
|
IMATECH POLICIES & TERMS
Credit Card Processing
Payment Gateway
E-Commerce